|
Wendover Road Roundabout Works
With the bridge works progressing well, the focus has turned to the completion of Wendover Road roundabout. As has been reported in previous bulletins, this work has been and continues to be hampered by a number of challenges, especially utilities. The team has been working closely with the utilities and the Council's streetworks team to identify a programme of work that means it can be undertaken safely whilst seeking to minimise disruption to road users.
To construct a roundabout on top of an existing busy road will always lead to some disruption. The work includes; installing new drainage pipes, lengthening an existing drainage culvert under the Wendover Road, diverting utilities, new road and footway construction, street lighting, traffic signals for the 3 new pedestrian crossings, acoustic fencing, traffic signs and road markings.
The initial plan involved 3 weeks of 24/7 3 way temporary traffic signals, during school term time, followed by a further 3 weeks of off peak 3 way temporary signals as well as other periods of disruptive work during term time. Due to the site layout, the signals on Wendover Road would need to have been nearly 300m apart leading to lots of lost time in each sequence of the signals to allow vehicles to clear that length.
Recognising the impact that around 6 weeks of disruptive signals could have, the team has been looking at ways to reduce this by maximising the work undertaken under the current temporary traffic management arrangements, re-sequencing the works and undertaking works during school holiday time.
Whilst the team has reduced the duration of work that requires traffic management, there will still be disruption caused, for which the SEALR team apologises.
Some works were undertaken on the weekend of 17/18 January using two way signals to undertake utility diversion works.
Works will also continue for the rest of January and early February using the current traffic management arrangements which allows 2 way traffic. These works on the West side of the roundabout include installing lighting columns, electrical works for the lighting and traffic signs, lower layers of road construction and some works to the drainage culvert South of the roundabout.
The planned temporary traffic management arrangements are:
February Half Term
0600 Saturday 14 February to 1800 Sunday 22 February - Road closed 24/7
Easter holiday
0600 Saturday 28 March to 1800 Sunday 12 April - Road closed 24/7
The diversion route is Wendover Road, Mandeville Road, Lower Road, Station Road, Wendover Road and vice versa and this will clearly be busy during the closure periods.
Nearby residents on Wendover Road will always be able to access their properties but, depending on the work taking place, may need to follow the diversion route. Access will also be maintained for Taylor Wimpey to access their development and emergency ambulances. Adjacent residents will be contacted by the team with further information prior to the closure.
During the February closure, it is intended that the noisiest works will be undertaken during the day. Works will also be undertaken at night with activities such as installing lighting columns, which should be less noisy. The works that will be undertaken during the February closure includes drainage works under the existing Wendover Road, extending the drainage culvert on the East side of the road, ducting for cables for street lighting and pedestrian crossing as well as fencing. Soon after the closure, the street lighting on the East side of the roundabout is expected to go live.
The traffic management will return to the arrangement is has been for some time with traffic using the roundabout Southbound and the old road Northbound with 2 way flow from 22 February. Under this arrangement, during week commencing 23 February there will be a significant amount of surfacing work on the West side of the roundabout to construct further layers of the carriageway construction.
Work on the roundabout will then start again in earnest under the road closure starting on Saturday 28 March. Over that weekend, the splitter islands on the North and South approaches to the roundabout will be completed alongside ducting work. Further road construction layers will also be installed before the final surfacing is laid which is expected to be undertaken at night. Final works include road markings and the installation of pedestrian crossings.
The only work remaining at the roundabout after Easter is some drainage works within the roundabout central island itself but these works will be undertaken by coning off the inner lane of the roundabout thus allowing 2 way flow and use of the roundabout.
Clearly the closure of a busy A road will cause disruption and inconvenience for which the team apologises but the result of this will be an operational roundabout on Wendover Road and this should be the last major roadworks required on Wendover Road and Lower Road by the SEALR project.
We apologise for any inconvenience related to these works and we encourage all road users to plan their journeys in advance and to allow some extra time. Please keep up to date with roadworks via one.network as well as following Buckinghamshire Highways on social media when not driving. Motorists are encouraged to keep an eye out for the electronic signs on site providing advanced information and to safely use sat navs as they can assist drivers with their journeys by providing live information on delays and to try to be patient if there are delays.
|