Bucks Council have issued this update on upcoming roadworks. They say it's part of a rolling programme of countywide work and some activities are extremely weather dependent, therefore dates shown are subject to change at short notice.
These dates may also be subject to change depending on the availability of materials and unforeseen circumstances out of our control. They apologise in advance for any inconvenience caused.
Micro Surfacing Prep
Green End Street, Aston Clinton (Monday 21 July)
Carriageway resurfacing works using a road closure in operation between 9am to 3:30pm.
Brook Street, Aston Clinton (Tuesday 22 July)
Carriageway resurfacing works using a road closure in operation between 7:30am to 7pm.
Conventional
London Road, Aston Clinton (Wednesday 16 July to Thursday 31 July)
Carriageway resurfacing works using a road closure in operation between 7pm to 6am.
Deans Close, Stoke Poges (Thursday 24 July to Friday 25 July)
Carriageway resurfacing works using a road closure in operation between 7:30am to 5pm.
Ivinghoe Freight Zone Phase 3
Replacement of signs and signposts at the below locations. Working hours are 9am to 3:30pm for all sites.
- B440/B489 Traveller's Rest Roundabouts - 21, 22, 23 and 24 July using multi-way traffic lights.
- B488 Westfield Rd RBT, Pitstone (Near Folly Farm) - 22, 25, and 28 July using multi-way traffic lights. 24 July the crew will be working from the verge.
Carriageway Resurfacing Works
Rose Drive, Eunice Grove, Kesters Road & Cavendish Road, Chesham (Monday 30 June to Wednesday 23 July)
Carriageway resurfacing works: Tuesday 15 July and Monday 21 July using a road closure, in operation Monday to Friday between 7am to 7pm.
The Parkway & Longstone Road, Iver Heath (Friday 11 July to Tuesday 29 July)
Carriageway resurfacing works using a road closure in operation between 7am to 7pm.
Herbert Road & Plantation Road, High Wycombe (Tuesday 15 July to Thursday 31 July)
Carriageway resurfacing works using a road closure in operation between 7am to 7pm.
Structures
Oxford Road Cycle Bridge, Aylesbury (Friday 30 June to Friday 22 August)
Replacement of bearings and minor repairs with topcoat painting for the main section of the bridge using a footpath closure with diversions in place for pedestrians, operation between 9am to 3:30pm.
Surface Dressing Prep
Outer Aylesbury Ring, (HOGSHAW) North Marston (Wednesday 23 July)
Carriageway resurfacing works using a road closure in operation between 7:30am to 5pm.
Surface Dressing
The headline treatment for this programme will commence on the dates below and will be followed by various days of sweeping to clear the loose stones and then a further road closure will be required to re-install the road markings and studs. These works will take place over a 2-3 week period depending on the collection of loose stone. Please see the current works that are in progress for next week:
Perry Lane, Bledlow, (Monday 21 July)
Carriageway surface dressing works using a road closure in operation between 7am to 7pm.
Kimblewick Road, Little Mead & Kimblewick, Little Meadle & Kimblewick (Monday 21 July)
Carriageway surface dressing works using a road closure in operation between 7am to 7pm.
Two Dells Lane, Ashley Green, (Tuesday 22 July)
Carriageway surface dressing works using a road closure in operation between 7am to 7pm.
Taplow Common Road, Burnham, (Tuesday 22 July)
Carriageway surface dressing works using a road closure in operation between 7am to 7pm.
Plane and Patch Resurfacing Schemes
Bockmer Road, Marlow Common (Monday 21 to Friday 25 July)
Carriageway resurfacing scheme using a road closure in operation between the hours of 7am to 7pm.
Streetlighting
Countywide Structural & Electrical Testing (Tuesday 27 May to Thursday 31 July)